Relatorio de materiais da zona
Relatorio de materiais da zona
Bom dia, como emitir a soma de materiais necessários em zona em parte do projeto ( exemplo da válvula 1 ate a válvula 5)
- jovivier
- Site Admin
- Posts: 897
- Joined: Thu Mar 12, 2009 2:57 pm
- Company: Lincoln Agritech Ltd, IRRICAD Software
- City / Town: Lincoln
- Location: Canterbury, New Zealand
- Contact:
Re: Relatorio de materiais da zona
Thank you for your question about partial Bill of Material reports.
There are two ways to do this:-
1. A one-off report
You can select the required zones on the screen, using the selection tools, and then action a BOM report. You also have the option to include a name for the report such "BOM for Zones 1-5 Only" so that it is clear what the report includes.
2. A more permanent designation
If the BOM reporting needs to be more permanent then use the "Scope" feature. A "Scope" flag is available in the hydraulic item dialogs. Hydraulic items can be set to:-
· Design + BOM
· Design Only
· BOM Only
This is a very useful tool for staged developments. For example, the pre-existing stage can be set to Design Only – meaning those materials will not appear in the BOM/Costing reports.
Changing the “Scope” for all selected hydraulic items can be achieved in one step:-
1. Select all hydraulic items to be changed e.g., by using a Select option.
2. Select Modify|Change – DO NOT use Change Type.
3. Change the “Scope” to that which is required.
4. Click [OK].
The IRRICAD Team
There are two ways to do this:-
1. A one-off report
You can select the required zones on the screen, using the selection tools, and then action a BOM report. You also have the option to include a name for the report such "BOM for Zones 1-5 Only" so that it is clear what the report includes.
2. A more permanent designation
If the BOM reporting needs to be more permanent then use the "Scope" feature. A "Scope" flag is available in the hydraulic item dialogs. Hydraulic items can be set to:-
· Design + BOM
· Design Only
· BOM Only
This is a very useful tool for staged developments. For example, the pre-existing stage can be set to Design Only – meaning those materials will not appear in the BOM/Costing reports.
Changing the “Scope” for all selected hydraulic items can be achieved in one step:-
1. Select all hydraulic items to be changed e.g., by using a Select option.
2. Select Modify|Change – DO NOT use Change Type.
3. Change the “Scope” to that which is required.
4. Click [OK].
The IRRICAD Team
Re: Relatorio de materiais da zona
OK MUITO OBRIGADO