Changing management does not clear BOM

Posted: Thu Oct 01, 2015 11:08 am
by JLarsen
I am having an issue with the BOM. Seems that whenever I clear the management and reassign flows that the bill of materials is showing 2x the quantities needed and or materials that are no longer needed with new management. Example: cleared management, reassigned flows for two sources instead of one, re-run mainline design. Design no longer requires 15" pipe. 15" pipe is still on BOM and quantities are incorrect.

Re: Changing management does not clear BOM

Posted: Thu Oct 01, 2015 11:09 am
by jovivier
Hi,

This is quite an unusual situation and I cannot make this happen here. Can you please email your design and database to Support@NelsonIrrigation.com or Support@IRRICAD.com for us to determine the cause of the issue.