IrriCad Team,
Is it possible in the near future to set up the Report Zone/Mainline BOM, to order the Area Numbers from 1.
Currently it does not order them correctly and can get hard to find certain areas in a large design.
Kind Regards,
Zone/Mainline BOM
- Matt Binder
- Posts: 29
- Joined: Fri Mar 13, 2009 11:45 am
- Company: Think Water Riverland
- City / Town: Waikerie
- Location: Waikerie, Australia
- Contact:
Zone/Mainline BOM
Matthew Binder
Think Water Riverland
Irrigation Designer
MOBILE: +61 429844976
Think Water Riverland
Irrigation Designer
MOBILE: +61 429844976
- jovivier
- Site Admin
- Posts: 919
- Joined: Thu Mar 12, 2009 2:57 pm
- Company: Lincoln Agritech Ltd, IRRICAD Software
- City / Town: Lincoln
- Location: Canterbury, New Zealand
- Contact:
Re: Zone/Mainline BOM
Hi Matt,
It shouldn't be too hard to do. We should be able to organise the report coding that way. I will have a look at it.
Kind regards,
Jo
It shouldn't be too hard to do. We should be able to organise the report coding that way. I will have a look at it.
Kind regards,
Jo
- Matt Binder
- Posts: 29
- Joined: Fri Mar 13, 2009 11:45 am
- Company: Think Water Riverland
- City / Town: Waikerie
- Location: Waikerie, Australia
- Contact:
Re: Zone/Mainline BOM
Thanks Jo.
Matthew Binder
Think Water Riverland
Irrigation Designer
MOBILE: +61 429844976
Think Water Riverland
Irrigation Designer
MOBILE: +61 429844976