BOM with costs -- running cost reported -1

Discussion about zone, mainline, management, costing and bill of materials reports.
Post Reply
Lia
Posts: 3
Joined: Tue Mar 05, 2024 10:12 am
Company: UCD
City / Town: Davis

BOM with costs -- running cost reported -1

Post by Lia »

Hi Jovivier,

May I know what could be the reason that the running cost of my sprinkler zone came out as -1? Thanks!
User avatar
phil
Site Admin
Posts: 41
Joined: Wed Apr 29, 2009 11:48 am
Company: Lincoln Agritech Ltd.
City / Town: Christchurch
Location: Lincoln, New Zealand
Contact:

Re: BOM with costs -- running cost reported -1

Post by phil »

The -1 indicates that an error was encountered when trying to calculate the running costs. The most common cause of this is if mainline design/analysis hasn't been run, this is required before the running costs can be calculated.

Phil
Lia
Posts: 3
Joined: Tue Mar 05, 2024 10:12 am
Company: UCD
City / Town: Davis

Re: BOM with costs -- running cost reported -1

Post by Lia »

Thank you!